In late June,the Everready Construction Co.submitted a $600,000 progress billing on a construction contract.On July 2,the bill was approved for payment,subject to a five percent retention,as provided by the contract.The amount that should be debited to Construction Expenditures is
A) $0.
B) $30,000.
C) $570,000.
D) $600,000.
Correct Answer: