Draw the network for this transportation problem.
Min
2XAX + 3XAY + 5XAZ+ 9XBX + 12XBY + 10XBZ
s.t.
XAX + XAY + XAZ ≤ 500
X BX + XBY + XBZ ≤ 400
XAX + XBX = 300
XAY + XBY = 300
XAZ + XBZ = 300
Xij ≥ 0
Correct Answer:
Verified