Which of the following is a general rule for crashing activities?
A) Crash only noncritical activities.
B) Crash activities with zero slack.
C) Crash activities with the greatest number of predecessors.
D) Crash the path with the fewest activities.
Correct Answer:
Verified
Q29: In deciding which activities to crash,one must
Q30: Slack equals
A)LF - EF.
B)EF - LF.
C)EF -
Q31: For an activity with more than one
Q32: Activities G,P,and R are the immediate predecessors
Q33: The earliest start time rule
A)compares the starting
Q35: Which of the following is NOT a
Q36: To calculate an activity's latest finish time,you
Q37: For an activity with more than one
Q38: We identify the critical path of a
Q39: Which of the following is always true