A project consists of five activities.Naturally the paint mixing precedes the painting activities.Also,both ceiling painting and floor sanding must be done prior to floor buffing.
a.Construct the PERT/CPM network for this problem.
b.What is the expected completion time of this project?
c.What is the probability that the project can be completed within 9 hr.?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: Crashing refers to an unanticipated delay in
Q3: The project manager should monitor the progress
Q4: The difference between an activity's earliest finish
Q8: The earliest finish time for the final
Q12: All activities on a critical path have
Q12: The earliest start time for an activity
Q19: A critical activity can be part of
Q20: The length of time an activity can
Q29: Consider the following PERT/CPM network with estimated
Q32: Consider a project that has been modeled
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents