The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path
Correct Answer:
Verified
Q31: The slack of any activity is the
Q32: When calculating the probability that a project
Q33: A normal distribution is usually used to
Q33: In order to determine the probability of
Q34: The latest finish of an activity is
Q35: A manager has decided that an activity
Q37: A forward pass is the process of
Q38: Crashing an activity will always reduce the
Q40: PERT/Cost is a systematic procedure to help
Q41: In a project network the critical path