PERT/CPM Can Answer Which of the Following Questions

Question 42

Multiple Choice

PERT/CPM can answer which of the following questions?


A) When do activities need to start and finish to meet a deadline?
B) How much delay can be tolerated for certain activities?
C) Given uncertainties,what is the probability that a project will finish on time?
D) What is the least expensive way to expedite a project to meet a deadline?
E) All of the above

Correct Answer: