The earliest start time for an activity is:
A) based on the length of the critical path
B) determined by the maximum of the earliest finish times of its immediate predecessors
C) determined by the maximum of the earliest finish times of its immediate successors
D) the same as the latest start time of its immediate predecessor
E) None of the above
Correct Answer:
Verified