Zany Brainy projected current year sales of 50,000 units at a unit sale price of $20.00.Actual current year sales were 55,000 units at $22.00 per unit.Actual variable costs,budgeted at $14.00 per unit,totaled $15.00 per unit.Budgeted fixed costs totaled $400,000 while actual fixed costs amounted to $420,000.
- What is the flexible budget variance for total expenses?
A) $55,000 unfavorable
B) $75,000 unfavorable
C) $55,000 favorable
D) $75,000 favorable
Correct Answer:
Verified
Q36: A flexible budget variance is the
Q37: Which of the following is NOT
Q38: The flexible budget variance is the
Q39: Assuming that all activity is within
Q40: Which budget is based on the
Q42: The Flashlight Company projected yearly sales
Q43: The Bird Brainz Corporation produces
Q44: Match each of the following terms
Q45: Kid Adventures Company projected current year
Q46: Breezy Fan Company manufactures ceiling fans
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents