Green Garden Supply budgeted three hours of direct labor per unit at $10.00 per hour to produce 500 units of product.The 500 units were completed using 1,600 hours of direct labor at $10.50 per hour.What is the direct labor efficiency variance?
A) $1,000 unfavorable
B) $1,000 favorable
C) $1,050 unfavorable
D) $1,050 favorable
Correct Answer: