The standard variable overhead cost rate for the Croskey Company is $12 per unit.Budgeted fixed overhead cost is $60,000.The Croskey Company budgeted 4,000 units for the current period and actually produced 3,860 finished units.What is the production volume variance? Assume the allocation base for fixed overhead costs is the number of units expected to be produced.
A) $3,780 favorable
B) $2,100 unfavorable
C) $2,100 favorable
D) $3,780 unfavorable
Correct Answer:
Verified
Q175: DeNozio Enterprises gathered the following
Q176: Canterberry Company uses the following overhead
Q177: The production volume variance is the
Q178: Royal Industries has the following information
Q179: Bolt Industries gathered the following
Q181: When recording the use of direct
Q182: Manufacturing cost variances are shown as
Q183: On a standard cost income statement,cost
Q184: Which department listed below would most
Q185: A standard cost income statement shows
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents