ABC uses job costing.Actual manufacturing overhead for the period is $19,600 while allocated manufacturing overhead is $18,700.What entry will close the manufacturing overhead balance?
A) Debit manufacturing overhead and credit work in process for $900
B) Debit manufacturing overhead and credit cost of goods sold for $900
C) Debit cost of goods sold and credit finished goods inventory for $900
D) Debit cost of goods sold and credit manufacturing overhead for $900
Correct Answer:
Verified
Q233: Here is some basic data
Q234: Job 299 started on June 1
Q235: Here is some basic data
Q236: Here is some basic data
Q237: The entry to record the purchase
Q239: Here is some basic data
Q240: Daniel Company uses a job cost
Q241: The engineering firm of Timothy &
Q242: Service firms follow the same approach
Q243: An interior designer spends 30 hours
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents