A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000.
-What is the total labor cost variance?
A) $9,000 unfavorable.
B) $2,000 unfavorable.
C) $8,000 unfavorable.
D) $6,000 unfavorable.
E) $3,000 unfavorable.
Correct Answer:
Verified
Q92: A company has established 5 pounds of
Q93: The standard materials cost to produce 1
Q94: The standard materials cost to produce 1
Q95: Use the following data to find the
Q96: Use the following data to find the
Q98: A job was budgeted to require 3
Q99: Use the following data to find the
Q100: The following company information is available for
Q101: Claymore Corp. has the following information
Q102: When there is a difference between the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents