The demand for Ballard's Glass Company's products varies, ranging from 10 to 20 windows a day with an average of 15. John Ballard works eight hours a day, five days a week. Each order is one window, and each window takes 26 minutes to install. What is the average waiting time in minutes?
A) 1.6
B) 4.4
C) 28.2
D) 56.3
E) 82.3
Correct Answer:
Verified
Q92: Two common operational measures of time are
Q95: Customer-response time is a measure of how
Q98: Manufacturing lead times can affect costs but
Q104: Several companies have adopted manufacturing lead time
Q105: The annual capacity of a machine is
Q110: The demand for Ballard's Glass Company's products
Q111: Which of the following are time drivers?
A)
Q114: The average waiting time is the average
Q118: Manufacturing lead time is the sum of
Q120: On-time performance is
A)the time it takes distribution
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents