In relation to the drum-buffer-rope concept that is used to maxamise flow through an organisational bottleneck, the statement that is correct is:
A) the 'drum' relates to the activity associated with only inserting materials into the constraint when needed
B) the 'buffer' is the activity of only maintaining a small amount of work in process
C) the 'rope' involves calculating the demand for materials according to specified lead times
D) All the statements are correct
Correct Answer:
Verified
Q25: Advantages of just-in time inventory management are
Q26: Activities performed under a value chain approach
Q27: Which of these is not associated with
Q28: The statement concerning lean accounting that is
Q29: It is correct that under a successful
Q31: The first stage in the lean accounting
Q32: A just-in-time system reduces costs in all
Q33: Under TOC a constraint that is a
Q34: The statement concerning the theory of constraints
Q35: The major disadvantage of the just-in-time system
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents