Burkett Company uses a standard cost system. Indirect costs were budgeted at $200,000 plus $15 per direct labor hour. The overhead rate is based on 10,000 hours. Actual results were: The variable overhead efficiency variance was
A) $10,000 F
B) $50,000 U
C) $35,000 U
D) $15,000 U
Correct Answer: