The Production Manager of CLR Calculated a Material and Unfavorable

Question 70

Multiple Choice

The production manager of CLR calculated a material and unfavorable variance of $4,000 with respect to the cost of direct materials. Which of the following is a likely next step for the production manager?


A) Identify and discipline the responsible employee
B) Take actions to prevent the variance from recurring
C) Ascertain the cause of the variance
D) Switch suppliers for direct materials

Correct Answer: