In a ____ or cost-plus-percentage of cost contract,the provider is reimbursed for all allowable costs and receives a percentage of the costs as a fee.
A) cost-plus-fee
B) cost-plus-fixed-fee
C) cost-plus-incentive-fee
D) cost-incentive-fee
Correct Answer:
Verified