Regier Company had planned for operating profit of $10 million in the master budget but actually achieved operating profit of only $7 million.
A) The flexible-budget variance for operating profit is $3 million favourable.
B) The static-budget variance for operating profit is $3 million unfavourable.
C) The flexible-budget variance for operating profit is $3 million unfavourable.
D) The static-budget variance for operating profit is $3 million favourable.
Correct Answer:
Verified
Q22: An unfavourable variance is conclusive evidence of
Q42: What might be unfavourable flexible-budget variance for
Q43: Answer the following questions using the
Q45: Answer the following questions using the
Q48: Answer the following questions using the
Q49: Answer the following questions using the
Q50: Answer the following questions using the
Q51: The _ budget uses the expected per
Q52: Which of the following is TRUE about
Q122: To prepare budgets based on actual data
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents