All of the following statements are true regarding dependent demand EXCEPT:
A) it is one of the underlying concepts of materials requirements planning (MRP) .
B) its concept can be understood by examining the bill of materials.
C) it can be calculated only by forecasting.
D) it is directly related to the demands of other stock-keeping units (SKUs) .
Correct Answer:
Verified
Q18: The bill of material (BOM) for
Q19: If A has a gross requirement to
Q20: Which of the following is least likely
Q21: Which of the following is an aggregate
Q22: _ are the total demand for an
Q24: The primary output of a materials requirements
Q25: Which aggregate planning strategy generally would result
Q26: Which lot sizing rule bases the order
Q27: If forecast demand exceeds the total factory
Q28: Which aggregate planning strategy sets production rate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents