Solved

A Company Is Faced with Seven Tasks That Have to Be

Question 69

Essay

A company is faced with seven tasks that have to be processed through two work centers, work center I and then center II. Assume work center I works continuously and that they are using Johnson's rule. Work centers need not change over to new jobs at the same time. Data appears below in hours:
 Task  Work Center I  Work Center II  A 2.583.47 B 1.665.84 C 2.712.41 D 5.521.99 E 3.387.62 F 5.221.73 G 2.891.11\begin{array}{|c|c|c|}\hline \text { Task } & \text { Work Center I } & \text { Work Center II } \\\hline \text { A } & 2.58 & 3.47 \\\hline \text { B } & 1.66 & 5.84 \\\hline \text { C } & 2.71 & 2.41 \\\hline \text { D } & 5.52 & 1.99 \\\hline \text { E } & 3.38 & 7.62 \\\hline \text { F } & 5.22 & 1.73 \\\hline \text { G } & 2.89 & 1.11 \\\hline\end{array}
a.What is the sequence of tasks?
b.What is the time in hours to complete all the tasks in both work centers?
c.What is the total idle time (in hours) for work center I?
d.What is the total idle time (in hours) for work center II?

Correct Answer:

verifed

Verified

a.Job order using Johnson's rule: B, A, ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents