Question 18

Multiple Choice

The critical path method (CPM) work breakdown structure consists of all of the following EXCEPT:


A) the number and definition of each project activity.
B) the normal time to complete each activity.
C) the immediate predecessors (i.e., the precedent relationships) .
D) the probabilities of completing each activity.

Correct Answer: