You are responsible for managing a project with the following activities (times are given in weeks) :
-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?
A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 12 weeks.
D) The project completion time becomes 16 weeks.
Correct Answer:
Verified
Q20: Shea is in charge of the
Q21: You are responsible for managing an
Q22: Shea is in charge of the
Q23: Which is NOT true of the critical
Q24: You are responsible for managing a
Q26: Which of the following is true of
Q27: Brian is assigned his first project. If
Q28: You are responsible for managing an
Q29: Which of the following is NOT an
Q30: You are responsible for managing a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents