The Huyden Company builds equipment to customer's specifications. On March 1, two jobs were in process with the following costs and information:
*Applied on the basis of machine hours
During March, Job 45 was started and Job 44 was completed and delivered to the customer. Job 43 was missing a part that was backordered and would be completed in June. The following costs were incurred in March:
It is Huyden's policy to bill clients at cost plus 40 percent.
Required:
a.
Calculate the overhead rate that Huyden is using.
b.
Calculate the overhead applied to each job during the month of March.
c.
Calculate the balance in work in process on March 31.
d.
What was the price of Job 44?
Correct Answer:
Verified
Q22: Explain the key considerations in establishing cost
Q60: A company incurred £20,000 of common fixed
Q61: Manchester Ltd. uses a job-order costing system
Q62: Rounders Company used the following information when
Q63: Explain the advantage of using multiple overhead
Q64: Although adding more cost pools to a
Q66: The support departments typically found in manufacturing
Q67: Crow Company applies factory overhead in its
Q68: Describe the differences between support and producing
Q70: The Greenbriar plant has two categories of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents