On July 1, 2015, Rhodes City approved the construction of a new library costing $8,000,000.The project was to be financed with a $4,000,000 general obligation bond issue and a matching state grant.
Required:
Record the following events in the Capital Project Fund for Rhodes City during 2015.
a.The city estimated that approximately one-fourth of the contract price would be paid for in the current fiscal year and that the bond issue will be sold this year.The project should be completed and the matching grant received next year.
b.The bonds are sold at 102 and premium to be used for future principal payment, forwarded to the Debt Service Fund.
c.A contract was signed to construct the library at a cost of $7,900,000 with a retained percentage of 10% until final inspection at completion.
d.The contractor submits a $1,000,000 progress billing.
e.The books are closed at year end.
Correct Answer:
Verified
Q45: The following selected events occurred in
Q46: The following selected events occurred in the
Q47: Consider the following events:
?
a.A portion of the
Q48: On 1-1-01, the City of Midville received
Q49: What is escheat property and how do
Q51: Given the following information for the
Q52: The City of Newport operates its own
Q53: Place a check mark in the appropriate
Q54: What reporting is required for the accounting
Q55: Consider the following transactions:
a.The Cline County Tax
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents