Zenich Corp manufactures laptops.The waiting time is 60 minutes before the start of production and the manufacturing lead time is 150 minutes per laptop.What is its manufacturing cycle efficiency?
A) 40%
B) 70%
C) 60%
D) 66.67%
Correct Answer:
Verified
Q95: The time from which a machine is
Q106: A time driver is any factor that
Q107: In the formula for calculating the average
Q108: Ventaz Corp manufactures glasses.The manufacturing cycle efficiency
Q114: Answer the following questions using the information
Q115: Customer response time is the time it
Q116: For a fast-food restaurant,the average waiting
Q117: Answer the following questions using the information
Q118: Manufacturing lead time is the sum of
Q118: Answer the following questions using the information
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents