Midtown,Inc.uses a predetermined overhead allocation rate of $68 per direct labor hour.In January,the company completed Job A23 which utilized 24 direct labor hours.Which of the following correctly describes the journal entry to allocate overhead to the job?
A) debit Finished Goods Inventory $1,632 and credit Manufacturing Overhead $1,632
B) debit Manufacturing Overhead $68 and credit Work-in-Process Inventory $68
C) debit Work-in-Process Inventory $1,632 and credit Manufacturing Overhead $1,632
D) debit Cost of Goods Sold $68 and credit Finished Goods Inventory $68
Correct Answer:
Verified
Q58: Norman Manufacturing reports the following data
Q59: Aaron,Inc.estimates direct labor costs and manufacturing overhead
Q63: Iglesias,Inc.completed Job 12 on November 30.The
Q65: Archangel Manufacturing calculated a predetermined overhead
Q66: Irene Manufacturing uses a predetermined overhead
Q67: Manufacturing overhead costs are allocated to the
Q67: Sybil,Inc.uses a predetermined overhead allocation rate to
Q68: When a job order costing system is
Q72: Which of the following will be categorized
Q77: Manufacturing overhead is allocated by debiting the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents