Forsyth,Inc.uses estimated direct labor hours of 245,000 and estimated manufacturing overhead costs of $1,200,000 in establishing its predetermined overhead allocation rate for the year.Actual results showed the following: The number of direct labor hours worked during the period was ________.(Round any intermediate calculations to two decimal places,and your final answer to the nearest whole number.)
A) 245,000 hours
B) 168,367 hours
C) 163,265 hours
D) 237,575 hours
Correct Answer:
Verified
Q113: When a job is completed,the total cost
Q114: Haverhill Products completed Job 440 and several
Q115: On January 1,Biden,Inc.'s Work-in-Process Inventory account had
Q116: In a machine-intensive production environment,the most accurate
Q117: The predetermined overhead rate is calculated _.
A)
Q119: When goods are transferred from the Work-in-Process
Q120: At the beginning of the year,Judge
Q121: Leonard Manufacturing Systems uses job order costing
Q122: On June 30,Cleopatra,Inc.finished Job 70 with total
Q123: During the year,a company incurred $520,000 of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents