Solved

Which of the Following Statements Is CORRECT

Question 15

Multiple Choice

Which of the following statements is CORRECT?


A) A sunk cost is any cost that was expended in the past but can be recovered if the firm decides not to go forward with the project.
B) A sunk cost is a cost that was incurred and expensed in the past and cannot be recovered if the firm decides not to go forward with the project.
C) Sunk costs were formerly hard to deal with but now that the NPV method is widely used, it is possible to simply include sunk costs in the cash flows and then calculate the PV of the project.
D) A good example of a sunk cost is a situation where Home Depot opens a new store, and that leads to a decline in sales of one of the firm's existing stores.
E) A sunk cost is any cost that must be expended in order to complete a project and bring it into operation.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents