The WBS is ____ of deliverables or end items that will be accomplished or produced by the project team or contractor during the project.
A) serial list
B) a hierarchical tree
C) network diagram
D) control system
Correct Answer:
Verified
Q81: The work packages are at a level
Q82: Once the project scope document has been
Q83: The work packages are at a level
Q84: The _ at a level of a
Q85: In order to prevent poor quality and
Q87: The lowest-level work item of any one
Q88: _ is a structured approach for organizing
Q89: The project scope document defines _ in
Q90: To help assure quality, the project quality
Q91: A _ emphasizes who is responsible for