Solved

Earliest Finish Time (EF)is the Earliest Time by Which a Specific

Question 54

Multiple Choice

Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated


A) by subtracting the activity's estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - Estimated Duration.
B) by subtracting the activity's estimated duration to the activity's earliest start time: EF = ES - Estimated Duration.
C) by adding the activity's estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + Estimated Duration.
D) by adding the activity's estimated duration to the activity's earliest start time: EF = ES + Estimated Duration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents