Earliest finish time (EF) is the earliest time by which a specific activity can be completed, calculated
A) by subtracting the activity's estimated duration from the earliest finish time of the activity's predecessor: EF = EF predecessor - Estimated Duration.
B) by subtracting the activity's estimated duration to the activity's earliest start time: EF = ES - Estimated Duration.
C) by adding the activity's estimated duration to the earliest start time of the activity's succeeding activity: EF = ES succeeding activity + Estimated Duration.
D) by adding the activity's estimated duration to the activity's earliest start time: EF = ES + Estimated Duration.
Correct Answer:
Verified
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Q50: Calculate the earliest start for Task D
Q51: Calculate the latest start for Task D
Q52: Latest start time (LS)is the latest time
Q53: With projects for which there is a
Q55: Calculate the latest finish for Task B
Q56: Total slack for the project is the
Q57: Calculate the earliest start for Task B
Q58: Calculate the latest start for Task B
Q59: Earliest start time (ES)is the earliest time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents