Latest finish time (LF) is the latest time by which a specific activity must be
A) started in order for the entire project to be finished by its required completion time.
B) completed in order for the entire project to be finished by its required completion time.
C) started in order for the entire project to be started by its required completion time.
D) completed in order for the entire project to be started by its required completion time.
Correct Answer:
Verified
Q42: Throughout the performance of the project, some
Q43: Calculate the latest finish for Task D
Q44: The ES and EF times are determined
Q45: Calculate the earliest finish for Task D
Q46: The earliest start time for a specific
Q48: Latest start time is calculated by
A) subtracting
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Q50: Calculate the earliest start for Task D
Q51: Calculate the latest start for Task D
Q52: Latest start time (LS)is the latest time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents