Completion time (from start to finish) of a building remodelling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days.The probability that the project will be completed within 185 work-days is ___.
A) 0.0668
B) 0.4332
C) 0.5000
D) 0.9332
E) 0.9950
Correct Answer:
Verified
Q43: Within a range of z scores from
Q76: Completion time (from start to finish)of a
Q78: Suppose the total time to fill a
Q79: Sure Stone Tire Company has established that
Q82: The probability that someone will prefer Coke
Q84: Participants in a 2 day biking event,
Q84: The average time between phone calls arriving
Q97: The probability that someone will prefer Coke
Q99: The exponential distribution is an example of
Q102: Most graduate business schools require applicants to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents