A ground-wave radar unit developed by a defense contractor has four critical components.If any one component should fail the radar unit would be rendered ineffective.The component reliabilities are .982, .946, .913, and .969, respectively.
a.What is the system reliability?
b.If the reliability of the third component is changed from .913 to .950, what does the system reliability become?
c.If the company decides to build in system redundancy for the third component, what does the third component's reliability become now?
d.What is the system reliability with redundancy for the third component?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q81: An ATM machine provides four sequential steps
Q82: In a two-component parallel system, the overall
Q83: Given the diagram below, determine the system
Q84: Given the diagram below, determine the system
Q86: Given the diagram below, determine the system
Q87: The system reliability for a three-component series
Q88: Given the diagram below, what if components
Q90: An analysis of the current mortgage loan
Q91: A company is developing a new rocket
Q112: To create and deliver a service, four
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents