Question 47

Multiple Choice

Which of the following is not correct relating to bottleneck resources?


A) Should be scheduled first
B) An hour lost is an hour lost for the entire process or factory output
C) Use large order sizes
D) Should plan safety capacity

Correct Answer:

verifed

Verified