Jack's Ice Cream Parlor produces two types of ice cream on a contract basis for a major restaurant chain using a large blender.A batch of ice cream A requires a setup time of 45 minutes, a process mixing time of 1.2 minutes per gallon, and 50 gallons are made per day.Ice cream B requires the same machine to be cleaned and setup which takes 30 minutes, a process mixing time of 2 minutes per gallon, and 100 gallons produced per day.
a.Compute the capacity required.
b.What percentage of total capacity required is setup time?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q61: An assembly line normally operates two shifts
Q61: A machine in a job shop is
Q64: C&M Machining is developing plans for a
Q68: A pharmacy lab is used for only
Q69: Define capacity including the two ways it
Q69: A food packaging plant has planned shipments
Q75: An order fulfillment process normally operates two
Q82: An assembly line normally operates two shifts
Q85: For a Marriott hotel call center, the
Q87: Define the Theory of Constraints (TOC). How
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents