The county government has decided to redo the street you live on and plans to block the street off which causes you and your neighbor's considerable inconvenience.The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days.Which one of the following statements is true?
A) The expected duration of the project is 30 + 22 + 16 = 68 days.
B) Path A-B-C-H is the critical path.
C) Path A-D-E-H has the most slack time.
D) Path A-F-G-H is the critical path.
Correct Answer:
Verified
Q22: Which of the following is not an
Q23: We should not crash activities on the
Q24: Which of the following is incorrect regarding
Q25: Which of the following is not a
Q26: Which statement is true regarding activities not
Q28: Which of the following is not considered
Q29: A project has three paths.A-B-C has a
Q30: A type of organization that can result
Q31: Which step in the project management process
Q90: The slack for an activity is equal
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents