The county government has decided to redo the street you live on and plans to block the street off which causes you and your neighbor's considerable inconvenience.The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days.Which one of the following statements is true?


A) The expected duration of the project is 30 + 22 + 16 = 68 days.
B) Path A-B-C-H is the critical path.
C) Path A-D-E-H has the most slack time.
D) Path A-F-G-H is the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents