Data regarding the activities for a project are presented below.The times are in weeks.The critical path for this project is A - D - H - I - J - K.
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q38: Which of the following is least related
Q39: A type of organization which "loans" resources
Q40: Which is incorrect regarding the critical path?
A)Shortest
Q41: Explain the role of the project managers
Q45: The following network shows all the major
Q46: Consider the project network and data shown
Q81: Describe the four major steps in the
Q94: Explain the purpose of Gantt charts.
Q95: Explain the three time estimates used to
Q96: Define a project. Give some non-manufacturing or
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents