If a company selects either of Project 1 or Project 2 (or both) , then either Project 3 or Project 4 (or both) must also be selected. Which of the following constraints enforce this condition?
A) X1 + X2 ≤ 2(X3 + X4)
B) X1 + X2 ≤ X3 + X4
C) X1 − X3 = X2 − X4
D) X1 + X2 + X3 + X4 ≤ 2
Correct Answer:
Verified
Q12: A vendor offers 5 different prices per
Q13: Specifying suboptimality tolerances can be useful if
Q14: For maximization problems, the optimal objective function
Q15: An ILP problem has 5 binary decision
Q16: The default value of suboptimality tolerance in
Q18: Values of the binary integer variable are
Q19: One useful feature of Analytic Solver Platform
Q20: A practical way of dealing with the
Q21: Pure IP formulation requires that:
A) all decision
Q22: How are general integrality requirements indicated in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents