A company wants to build a new factory in either Atlanta or Columbia.It is also considering building a warehouse in whichever city is selected for the new factory.The following table shows the net present value NPV)and cost of each facility.The company wants to maximize the net present value of its facilities,but it only has $16 million to invest.
Variable Decision
NPV
$million)
Cost $million)
X1 Factory in Columbia 3 10
X2 Factory in Atlanta 4 8
X3 Warehouse in Columbia 2 6
X4 Warehouse in Atlanta 1 5
Based on this ILP formulation of the problem what is the optimal solution to the problem?
MAX: 3 X1 + 4 X2 + 2 X3 + X4
Subject to: 10 X1 + 8 X2 + 6 X3 + 5 X4 ≤ 15
X1 + X2 = 1 X3 + X4 ≤ 1 X3 − X1 ≤ 0 X4 − X2 ≤ 0 Xi = 0,1
Correct Answer:
Verified
Objective
Function Cost F...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q49: A company wants to build a new
Q52: A company wants to build a new
Q52: The optimal relaxed solution for an ILP
Q54: An investor has $500,000 to invest
Q55: A sub-problem in a B & B
Q55: A company needs to hire workers
Q56: A small town wants to build
Q57: A cellular phone company wants to
Q58: An investor has $500,000 to invest
Q84: A company has four projects, numbered 1
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents