Exhibit 15.1 The Following Questions Employ the AON Network and Partial Spreadsheet

Question 42

Multiple Choice

Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below. Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     -Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT) ? A)  To order activities in a project in terms of their completion time to facilitate scheduling of the activities. B)  To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule. C)  To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable. D)  To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities. Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.     -Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT) ? A)  To order activities in a project in terms of their completion time to facilitate scheduling of the activities. B)  To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule. C)  To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable. D)  To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
-Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT) ?


A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents