A company wants to use PERT to manage a project.They have developed the following spreadsheet for the problem.If The Risk Solver Platform RSP) is used,what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
A) =IFE3?C3-E3) /D3-B3) ,D3-SQRTD3-B3) *D3-C3) *1-E3) ) ,B3+SQRTD3-E3) *C3-B3) *E3) )
B) =IFE3?D3-B3) /C3-E3) ,B3+SQRTD3-E3) *C3-B3) *E3) ,D3-SQRTD3-B3) *D3-C3) *1-E3) ) )
C) =IFE3?C3-E3) /D3-B3) ,B3-SQRTD3-E3) *C3-B3) *E3) ,D3+SQRTD3-B3) *D3-C3) *1-E3) ) )
D) =PsiTriangularB3,C3,D3)
Correct Answer:
Verified
Q13: Exhibit 14.13
The following questions use the information
Q21: Exhibit 15.2
The following questions employ the AON
Q27: Exhibit 15.1
The following questions employ the AON
Q28: Exhibit 15.2
The following questions employ the AON
Q30: Exhibit 15.1
The following questions employ the AON
Q35: If the following project must be completed
Q43: Exhibit 15.2
The following questions employ the AON
Q45: Exhibit 15.1
The following questions employ the AON
Q57: Exhibit 15.2
The following questions employ the AON
Q59: Exhibit 15.1
The following questions employ the AON
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents