Bay City Construction,Inc.,a contractor,asks Cool Electric,a subcontractor,to provide certain services.Nothing is said about payment.Cool provides the services,but Bay City refuses to pay.In Cool's suit to recover,the chief issue is most likely to be whether these parties had
A) a formal contract.
B) an express contract.
C) an implied contract.
D) a voidable contract.
Correct Answer:
Verified
Q51: GR8 Marketing Company and Brainfreeze Tunes,Inc.,sign a
Q54: Clay offers to pay Dot $50 for
Q55: Kelly tells Jimmy she will pay him
Q57: Jonah tells Levi he will give him
Q58: On behalf of the rock group Uno,their
Q60: Scot and Tiffany enter into an implied
Q61: Cody signs and returns a letter from
Q62: Livewire Company and McCoy's Candy,Inc.,sign a document
Q63: Demi promises to buy a house from
Q64: Vernon claims that his contract with Ulani
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents