Job #305 was budgeted to require 3.5 hours of labor at $11 per hour.However,it was completed in 3 hours by a person who worked for $14 per hour.
a.What is the total labor cost variance for Job #305?
b.Calculate the direct labor rate and efficiency variance for this job.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q111: Whistler Company determined that in the production
Q123: Based on predicted production of 25,000 units,
Q129: DT Co.produces picture frames.It takes 3 hours
Q130: Thomas Co.provides the following fixed budget data
Q131: Provide at least one cause of direct
Q132: Big Bend Co.fixed budget for the year
Q133: A company's budget for 60,000 units of
Q135: Elroy Co.has prepared the following fixed
Q136: Use the following cost information to
Q138: Stanton Co.produces and sells two lines
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents