RC CorpUses a Job Order Cost Accounting System

Question 118

Essay

RC Corp.uses a job order cost accounting system.During the month of April,the following events occurred:
A. Purchased raw materials on credit, $32,000.
B. Raw materials requisitioned: $25,800 as direct materials (Job 1:$4,200, Job 2: $7,500, Job 3: $3,600 and Job 4: $10,500) and $10,500 indirect materials.
C. Paid factory payroll for the month totaling $37,700 which includes $8,200 indirect labor.
D. Assigned the factory payroll to jobs and overhead. (Job 1:$7,000, Job 2: $9,800, Job 3: $3,000 and Job 4: $9,700)
E. Overhead was assigned at a rate of 50% of direct labor cost.
Determine the total cost of each job.

Correct Answer:

verifed

Verified

Job 1: $4,200 + 7,000 + (7,000...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents