Twenty-thousand dollars was budgeted for the office renovation that had a task contingency multiplier of 1.3.The estimated cost of the task must be:
A) About $15,400.
B) About $26,000.
C) About $22,800.
D) About $18,600.
Correct Answer:
Verified