A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the late finish for the Plant Posts activity?
A) 13.3 days
B) 8 days
C) 20.83 days
D) 22 days
Correct Answer:
Verified
Q66: Q73: Use the information in the table Q74: A project has the precedence requirements Q75: The least amount of float is found: Q76: Use the information in the table to Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents![]()