Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project. 
A) $16,900
B) $14,900
C) $14,400
D) $13,200
Correct Answer:
Verified
Q42: Use the earned value table to determine
Q44: The first step in earned value management
Q45: Use the earned value table for Project
Q45: The budget variance is calculated as:
A)Earned value
Q46: At the end of week 20,this project
Q49: Use the data to calculate the
Q49: In earned value management analysis,the cumulative amount
Q50: The project baseline is established by combining
Q52: Use the data to calculate the
Q58: Duration (weeks)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents