Which statement does NOT accurately describe the internal rate of return for a project?
A) If the internal rate of return is less than the required rate of return, the project will be rejected.
B) If the internal rate of return is more than the required rate of return, the project will be accepted.
C) If the internal rate of return is equal to the required rate of return, the net present value of the project is zero.
D) If the internal rate of return is equal to the required rate of return, the net present value of the project is positive.
Correct Answer:
Verified
Q99: Present Value Tables
Present value of $1
Q100: Ostead Company
Ostead Company is considering an
Q101: What is characteristic of the measurement and
Q102: Refer to Cantar, Inc. What is the
Q103: What term refers to the interest rate
Q105: Jackson Company is considering a project requiring
Q106: What is NOT a benefit of postaudits
Q107: The Picture Company is considering the purchase
Q108: Which of the following compares the actual
Q109: Boleyn Company
Boleyn Company is considering two
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents