An assembly line with 28 operations is to be balanced. The total amount of time required for all 28 operations is 39 minutes. The longest operation takes 2.2 minutes and the shortest takes 0.8 minutes. The line will operate for 450 minutes per day. 1. Determine the minimun and maximu cycle time.
2. What is the output rate if the cycle tine is set at 2.2 minutes?
A) min cycle time = 0.8; max cycle time = 39; output rate = 204.5
B) min cycle time = 2.2; max cycle time = 39; output rate = 204.5
C) min cycle time = 2.2; max cycle time = 31.2; output rate = 562.5
D) min cycle time = 0.8; max cycle time = 2.2; output rate = 562.5
Correct Answer:
Verified
Q3: An assembly line with 28 activities is
Q26: Which of the following is not a
Q27: A line balancing solution has been developed
Q31: A _ layout consists of a functional
Q32: A _ layout is an arrangement based
Q33: CRAFT is a process layout technique that
Q34: All of the following are common objectives
Q40: The production of large goods such as
Q67: Ergonomics is the science that is concerned
Q80: Teams are a way of accomplishing job
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents