A Local Manufacturer Produces Two Different Products on the Same \quad

Question 87

Essay

A local manufacturer produces two different products on the same production line. Product A requires .5 hours of labor while product B requires .8 hours of labor. The total labor available in any one week is 600 hours. The production manager has just developed the following weekly production schedule and has asked you to check and see if there is any week in this schedule where the production system will be overloaded or underloaded.
\quad \quad \quad \quad \quad \quad \quad \quad \quad  Week \text { Week }
 End Item 123456 A 900500800900600600 B 175150300200375375\begin{array}{|c|c|c|c|c|c|c|}\hline \text { End Item } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { A } & 900 & 500 & 800 & 900 & 600 & 600 \\\hline \text { B } & 175 & 150 & 300 & 200 & 375 & 375 \\\hline\end{array}
a. What is the total hourly load on the line in week 2?
b. In what (weeks) is the line overloaded?

Correct Answer:

verifed

Verified

a. 370
Rou...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents